Jambmaths question:
The time taken to do a piece of work is inversely proportional to the number of men employed. If ity takes 30 men to do a piece of work in 6days, how many men are required to do the work in 4 days
Option A:
35
Option B:
60
Option C:
20
Option D:
45
Jamb Maths Solution:
$\begin{align} & \text{Let the number of men be}N\text{and the time taken to be}T \\ & T\propto \frac{1}{N};\text{ }T=\frac{K}{N}\text{ }\!\!\{\!\!\text{ }K=proportionality\text{ }constant\} \\ & 6=\frac{K}{30} \\ & K=6\times 30=180 \\ & \text{When }T=4 \\ & 4=\frac{180}{N};\text{ }N=\frac{180}{4}=45 \\\end{align}$